Register
QZ08-084
Carmacks Copper Ltd.
Nature of Application: Quartz Undertaking
VOLUME I
1. APPLICATION
- 1.1 Schedule 4 and letter, 09.10.29
- 1.2 Water Use Application - Information Sheet
- 1.2.1 Proposed Water Use Licence
- 1.2.2 Project Brief - Part A / Part B / Part C
- 1.2.3 Main Report - Volume 1, dated October 2009 - Part A / Part B
- 1.2.3.1 Table of Contents
- 1.2.3.2 Corporate Profile
- 1.2.3.3 Project Scope
- 1.2.3.4 Project Description - Part A / Part B / Part C / Part D / Part E / Part F / Part G / Part H / Part I / Part J
- 1.2.3.5 Environmental Setting and Monitoring - Part A / Part B / Part C / Part D / Part E / Part F / Part G / Part H / Part I / Part J / Part K / Part L / Part M
- 1.2.3.6 Proposed Licence Specifications
- 1.2.3.7 Acknowledgement and Certification
- 1.2.3.8 References
top
VOLUME II
Note: Supporting Appendices A - G, as provided by the applicant on 09.11.09, have been assigned the following exhibit numbers:
- 1.3 Appendix A - Project Drawings
- 1.4 Appendix B - Western Copper Corporation Safety and Environmental Policy
- 1.5 Appendix C - Project Design Criteria
- 1.5.1 Appendix C-1 - Golder Reliance on Technical Reports
- 1.5.2 Appendix C-2 - Existing Design Criteria
- 1.5.3 Appendix C-3 - Process Criteria
- 1.6 Appendix D - Surface Water Management
- 1.6.1 Appendix D-1 - Preliminary Surface Water Management Plan (Operations)
- 1.6.2 Appendix D-2 - Sediment Control Ponds Preliminary Design and Operation
- 1.6.3 Appendix D-3 - HLF and Events Pond Spillways Preliminary Design
- 1.6.4 Appendix D-4 - MSDS for Flocculants
- 1.7 Appendix E - Site Hydrology and Water Balance
- 1.7.1 Appendix E-1 - Williams Creek Site Hydrology Update CCL-CC6
- 1.7.2 Appendix E-2 - Water Balance Update CCL-CC7
- 1.7.3 Appendix E-3 - Site Water Balance
- 1.7.4 Appendix E-4 - Site Water Balance Update
- 1.7.5 Appendix E-5 - Preliminary Closure Operations Water Balance for the Heap Leach Rinsing and Neutralization Operations
- 1.7.6 Appendix E-6 - Williams Creek Site Hydrology Update
- 1.8 Appendix F - Williams Creek Treated & closure Water Discharge Regime & Recommendations; including Appendix 1 - Williams Creek Geochemistry
- 1.9 Appendix G - Williams Creek Natural Attenuation Capacity
top
VOLUME III
- 1.10 Appendix H - Water Treatment System
- 1.10.1 Attachment A - Treatability Test Results, March 2007 Report
- 1.10.2 Attachment B - Bench Scale Treatability Study Report, Neutralization Testwork, March 2008
- 1.11 Appendix I - Discharge Predictions
- 1.11.1 Appendix I-1 - Discharge Predictions and Downstream Water Quality
- 1.11.2 Appendix I-2 - Long-Term Draindown Simulation
- 1.12 Appendix J - Site-Specific Water Quality Objective for Copper in Williams Creek
- 1.13 Appendix K - Evaluation of Water Quality and Development of Background-Based Site-Specific Water Quality Objectives for Williams Creek
- 1.14 Appendix L - Water Effect Ratio Testing
- 1.14.1 Appendix L-1 - Water Effect Ratio Testing of Copper in Williams Creek
- 1.14.2 Appendix L-2 - Review of Water Effect Ratio Testing & Derivation of a Site-Specific Water Quality Objective for Copper in Williams Creek
- 1.14.3 Appendix L-3 - Water Effect Ratio - Copper (Results & Data)
VOLUME IV
- 1.15 Appendix M - 2007 Geotechnical Investigation
- 1.15.1 Section 1 - Introduction
- 1.15.2 Section 2 - Surface Conditions and Proposed Development
- 1.15.3 Section 3 - Geotechnical Investigation
- 1.15.4 Section 4 - Subsurface Conditions
- 1.15.5 Section 5 - Potential Borrow Areas
- 1.15.6 Section 6 - Closure
- 1.15.7 Tables 1 to 22
- 1.15.8 Figures and Drawings
- 1.15.9 Appendix I - Borehole and Monitoring Logs
- 1.15.10 Appendix II - Test Pit Logs, Photographs and Sketches
- 1.15.11 Appendix III - Laboratory Testing Results
- 1.15.12 Appendix IV - Ground Temperature Profiles & Thermistor String Calibration Sheets
top
VOLUME V
- 1.16 Appendix N - Quartz Mining License & Associated Documents/Approvals
- 1.16.1 Appendix N-1 - Quartz Mining License QML-0007
- 1.16.2 Appendix N-2 - Construction Site Plan
- 1.16.2.1 Appendix A - Project Drawings
- 1.16.2.2 Appendix B - Western Copper Corporation Claims Affected by Construction
- 1.16.2.3 Appendix C - Civil Design Criteria
- 1.16.2.4 Appendix D - Construction Surface Water Management Plan
- 1.16.2.5 Appendix E - Waste Management Plan
- 1.16.2.6 Appendix F - ARD Protocol for Evaluation of Construction Materials
- 1.16.2.7 Appendix G - Preliminary Design Waste Rock Storage Area
- 1.16.2.8 Appendix H - Detailed Closure and Reclamation Plan
- 1.16.2.9 Appendix I - Environmental Monitoring Program
- 1.16.2.10 Appendix J - Health and Safety & Emergency Response Guide
- 1.16.3 Appendix N-3 - Results of Field Investigations for WRSA (Appendix I to Preliminary Design Waste Rock Storage Area)
- 1.16.4 Appendix N-4 - YG Letters of Approval for the Construction Site Plan & Preliminary Detailed Closure and Reclamation Plan
- 1.16.5 Appendix N-5 - Annual Inspection Report - August 13, 2009
- 1.16.6 Appendix N-6 - Erosion and Sediment Control Measures, September 2009
top
VOLUME VI
- 1.17 Appendix O - Results of Geochemical Test Work
- 1.18 Appendix P - Baseline Data
- 1.18.1 Appendix P-1 - Environmental Monitoring Program Update & Data Summary Revision No. 1
- 1.18.2 Appendix P-2 - Environmental Monitoring Program Update & Data Summary Revision No. 2
- 1.18.3 Appendix P-3 - Environmental Monitoring Program Update & Data Summary Revision No. 3
- 1.18.4 Appendix P-4 - Environmental Monitoring Program Update & Data Summary Revision No. 4
- 1.18.5 Appendix P-5 - Water Quality Database to 2008-Digital Excel File on CD - Part A / Part B
- 1.19 Appendix Q - Assessment of Hydrogeological Conditions During Operation and Closure
- 1.20 Appendix R - Stability Analysis Sludge Containment Embankment
- 1.21 Appendix S - Thermal Analysis
- 1.21.1 Appendix S-1 - Thermal Analysis of the Waste Rock Storage Area
- 1.21.2 Appendix S-2 - Summary of Thermistor Readings
- 1.22 Appendix T - Heap Leach Facility
- 1.22.1 Appendix T-1 - Heap Leach Facility Cell Layout and Grading
- 1.22.2 Appendix T-2 - Summary of Superceded Sections of Preliminary Design Report Heap
- 1.22.3 Appendix T-3 - General Implications of 2007 Geotechnical Investigation Program for the Preliminary Heap Leach Facility Design
- 1.22.3.1 Letter from Golder Assoc. to J.Clegg, dated August 25, 2009
- 1.22.3.2 Final Report on Preliminary Design Report, Heap Leach Facility Carmacks Copper Project, Volume 1
- 1.22.3.2.1 Section 1 - Introduction
- 1.22.3.2.2 Section 2 - Yukon Regulatory Requirements
- 1.22.3.2.3 Section 3 - Design Objectives
- 1.22.3.2.4 Section 4 - Design Considerations and Criteria
- 1.22.3.2.5 Section 5 - Preliminary Design
- 1.22.3.2.6 Section 6 - Construction Considerations
- 1.22.3.2.7 Section 7 - Operational Considerations
- 1.22.3.2.8 Section 8 - Closure
- 1.22.3.2.9 Figures 1 to 16
top
VOLUME VII
- 1.22.4 Appendix T-4 - Heap Leach Facility Preliminary Design Report, Volume 2
- 1.22.4.1 Appendix I - Thermal Analysis
- 1.22.4.2 Appendix II - Foundation Assessment
- 1.22.4.3 Appendix III - Heap Leach Pad Slope Stability Analysis
- 1.22.4.4 Appendix IV - Hydrogeologic Assessment
- 1.22.4.5 Appendix V - Liner System Assessment
- 1.22.4.6 Appendix VI - Water Balance
- 1.22.4.7 Appendix VII - Geochemical Test Results
- 1.22.5 Appendix T-5 - Heap Leach Facility Progress Report Detailed Stacking/Leaching Plan
- 1.22.6 Appendix T-6 - Heap Leach Facility Summary of Stacking Plan and Proposed Equipment
- 1.22.7 Appendix T-7 - Summary of Laboratory Test Results - HLF Liner System
- 1.22.8 Appendix T-8 - One-Dimensional Foundation Assessment - Heap Leach Facility
- 1.22.9 Appendix T-9 - Two-Dimensional HLF Settlement Analysis
- 1.22.10 Appendix T-10 - Laboratory Test Data Summary (Ore Characteristics)
- 1.22.11 Appendix T-11 - Stability Heap Leach Facility and Events Pond
- 1.22.12 Appendix T-12 - Volumes, Permeability and Filter Criteria for HLF Liner System
VOLUME VIII
- 1.23 Appendix U - Groundwater Monitoring and Supply Wells
- 1.24 Appendix V - Adaptive Management Plan Framework
- 1.25 Appendix W - Evaluation of Mineralogy
- 1.25.1 Appendix W-1 - Rinsed Column Mineralogy
- 1.25.2 Appendix W-2 - Technical Memo - Mineralogy of Leach Residues
- 1.25.3 Appendix W-3 - Evaluation of the Mineralogy of a Sample of Carmacks Acid Leach Residue
- 1.26 Appendix X - Operational Winter Temperature Profiles of Pilot Test Leach
- 1.27 Appendix Y - Neutralization Testwork
- 1.27.1 Appendix Y-1 - Leaching and Decommissioning of Samples from Carmacks Oxide Copper Project
- 1.27.2 Appendix Y-2 - Detoxification and Rinsing Testwork Report
- 1.27.3 Appendix Y-3 - Heap Rinsing Additional Information
- 1.27.4 Appendix Y-4 - Sequential Leaching and Other Characterization of Drill Ore Samples
- 1.27.5 Appendix Y-5 - Rinse Tests Following Acid Leaching In 1 Meter Columns 3 & 6
- 1.27.6 Appendix Y-6 - History Carmacks Rinsing and Neutralization Testwork
- 1.28 Appendix Z - YESAB Screening Report and Recommendation
VOLUME IX
2.0 SUPPLEMENTAL INFORMATION
- 2.1 Supplemental Information - Response to K. Boutilier, YWB email dated November 25, 2009
- 2.2 Supplemental Information -Response to C. Scheu, Water Quality/ Flow Information, 10.02.05
- 2.3
Supplemental
Information -Response to C. Scheu, Request for Additional Reports,
10.02.05
- 2.3.1 EcoMetrix Report, 10.02.05
- 2.3.2 Lorax Report -Technical Review of Closure Plan and Additional Information, 10.02.05
- 2.4 Supplemental Information -Response to C. Scheu - Exhibit 4.6, Flow data clarification, 10.02.10
- 2.5 Supplemental Information -Response to C. Scheu - Exhibit 4.7, Draft Contingency Plan, January 18, 2010, 10.02.10
- 2.6 Supplemental Information - Updated Draft Licence provided by Carmacks Copper Ltd. Replacing Exhibit 1.2.1, 10.02.15 *Late filing; accepted at Public Hearing 10.02.15
- 2.7 Supplemental Information - Discharge/Temperature Graphs and associated data provided by Carmacks Copper Ltd., 10.02.16 *Late filing; accepted at Public Hearing 10.02.16
- 2.8 Supplemental Information – Photographs of Heap Foundation Scale Model on display at the Public Hearing dated 10.02.15 *Late filing; accepted at Public Hearing 10.02.16
- 2.9 Supplemental Information – Document prepared by Environment Canada titled, The Export of Nutrients From Surface Coal Mines dated March 1988 *Late filing; accepted at Public Hearing 10.02.16
- 2.10 Supplemental Information – Figure 1 – Potential Settlement Under Heap Leach Facility, Indicating 3 Boreholes *Late filing; accepted at Public Hearing 10.02.17
- 2.11 Supplemental Information – Cost Estimate of Worst Case Closure Scenario *Late filing; accepted at Public Hearing 10.02.17 ~ requested by Board
- 2.12 Supplemental Information – Curriculum Vitae of Experts assisting Carmacks Copper Ltd. during the Public Hearing *Late filing; accepted at Public Hearing 10.02.18 ~ requested by Board
- 2.12.1 Brad A. Thrall, B.Sc., MBA
- 2.12.2 Jim Harrington, M.S. Biochemistry
- 2.12.3 David Petkovich, B.Sc. Marine Biology
- 2.12.4 John Hull, M.Sc. Geotechnical Engineering, B.Sc. Civil Engineering
- 2.12.5 Fiona Esford, M.A.Sc., P.Eng.
- 2.12.6 Pierre Stecko, M.Sc., CCEP, RPBio
- 2.13 Supplemental Information – Updated Water Balance Scenarios to reflect the discharge of Pit Flows to the Events Pond, 10.02.18 *Late filing; accepted at Public Hearing 10.02.18 ~ requested by Board
- 2.14 Supplemental Information – Estimate of Sludge Storage Depth for Concurrent Rinsing Options *Late filing; accepted at Public Hearing 10.02.18 ~ requested by Board
- 2.15 Supplemental Information – 2006 & 2007 Continuous Hydrological Data for Williams Creek sites W4 and W10, 10.02.18 *Late filing; accepted at Public Hearing 10.02.18 ~ requested by Board
- 2.16 Effect of Concurrent Rinsing - Data from Catalin Report *Late filing; accepted at Public Hearing 10.03.01 ~ requested by Board
3. PUBLIC NOTICES
- 3.1 Advertisement, 09.11.30
4. CORRESPONDENCE
- 4.1 Letter to Applicant requesting information/clarification, 09.11.18
- 4.2 Letter to Distribution List re: public hearing, 09.11.30
- 4.3 Letter to Parties re: Procedures of public hearing, 10.01.28
- 4.4 Letter to Applicant requesting additional reports, 10.02.03
- 4.5 Letter to Applicant requesting water quality / flow data, 10.02.04
- 4.6 Email to Applicant requesting flow data clarification, 10.02.08
- 4.7 Email to Applicant re: contingency plan, 10.02.09
top
VOLUME X
5. INTERVENTIONS
- 5.1 D. Smeeton, Department of Fisheries and Oceans Canada, Habitat and Enhancement Branch, 09.12.16
- 5.2 L. Rifkind, Yukon Conservation Society, 10.01.25
- 5.2.1 Attachment 1 - "Impacts of Copper on Aquatic. Ecosystems and Human Health" (Mining.com pp 25 - 28, Solomon Frances (2009)), 10.01.25
- 5.2.2 Attachment 2 - Treaty Between the Government of Canada and the Government of the United States of America Concerning Pacific Salmon, last updated January 27, 2009, 10.01.25
- 5.3 D. Gill, Selkirk First Nation, 10.01.25
- 5.4 R. Moar, Little Salmon Carmacks First Nation, 10.01.25
- 5.4.1 R. Moar, Little Salmon Carmacks First Nation, re. Citizens Concerns, 10.01.25
- 5.4.2 Predicted vs. Actual Performance of Three Mines Near The Carmacks Copper Heap Leach Project, 10.01.25
- 5.4.2.1 Appendix I - Resume and Company Profile for Bill Slater, 10.01.25
- 5.4.2.2 Appendix II - Excerpt from Minto Project - Type A Water Licence Application, Minto Explorations Ltd. February 1996, 10.01.25
- 5.4.2.3 Appendix III - Excerpts from Letter REport: Water Quality Prediction Modeling, Minto Mine Water Management Planning, Access Consulting Group, November 2009, 10.01.25
- 5.4.2.4 Appendix IV - Excerpts from 2009 Annual Water Licence Report, Water Use Licence QZ96-006, Minto Explorations Ltd., August 2009, 10.01.25
- 5.4.2.5 Appendix V - Data for water licence amendments No. 5 and No.6 provided to Robert Moar (LSCFN) by Colleen Roche (Capstone Mining Ltd.), Minto Explorations Ltd., 10.01.25
- 5.4.2.6 Appendix VI - Documents and Pages from Yukon Energy Mines and Resources Website, 10.01.25
- 5.4.2.7 Appendix VII - Excerpts from Detailed Decommissioning and Reclamation Plan, Revision 2, Minto Explorations Ltd., September 2009, 10.01.25
- 5.4.2.8 Appendix VIII - Excerpts from Mend Report No. 1.70.1 Investigation fo Predictions fro Acidic Drainage at the Vangorda Plateau, Sue Moodie and Bill Slater, April, 2008, 10.01.25
- 5.4.2.9 Appendix IX - Excerpts from Mt. Nansen Gold Mine, 1998 Effluent Quality Analysis Report, BYG Natural Resources Inc., July 1998, 10.01.25
- 5.4.2.10 Appendix X - Excerpts from 1998 Annual Report, Water Licence QZ94-004, BYG Natural Resources Inc., November 1994, 10.01.25
- 5.4.2.11 Appendix XI - Excerpts from Initial Environment Evaluation, Mt. Nansen Development, BYG Natural Resources Inc., November 1994, 10.01.25
- 5.4.2.12 Appendix XII - Excerpts from Dam Safety Assessment, Mount Nansen Tailings Facility near Carmacks, YT, EBA Engineering Consultants Ltd., May 2002, 10.01.25
- 5.4.3 Review of Project Application by James R. Kuipers P.E, dated January 24, 2010, 10.01.25
- 5.4.3.1 Exhibit 1 - Curriculum Vitae - James R. Kuipers P.E., 10.01.25
- 5.4.3.2 Exhibit 2 - Comparisons Report, 10.01.25
- 5.4.3.3 Exhibit 3 - Predictions Report, 10.01.25
- 5.4.4 Heap Leach Closure Workshop, 10.01.25
- 5.4.5 Copper Heap Leach Design - Hit or Miss? by ALTA Metallurgical Services, dated May 2002, 10.01.25
- 5.4.6 High Country News Article: The Short Life of Lisbon Valley, 10.01.25
- 5.4.7 Letter from Centre for Science in Public Participation, dated April 28, 2008 re: Review of Carmacks Copper Heap Closure Plan, 10.01.25\
- 5.4.8 Letter from Little Salmon Carmacks First Nation to S. Mills dated Feb. 6, 2008 Re: Draft Screening Report, 10.01.25
- 5.4.8.1 Review of Carmacks Copper Draft Screening Report by Bill Slater Environmental Consulting dated February 5, 2008, 10.01.25
- 5.4.8.2 Comments by Lionel Catalan, Ph.D, Eng. Re: rinsing/neutralization plan for Carmacks heap leach residues dated February 1, 2008, 10.01.25
- 5.4.9 Letter from Lionel Catalan, Ph.D, P.Eng, Re: Review of EcoMetrix Report to YESAB, dated April 9, 2008, 10.01.25
- 5.4.10 Chemosensory Deprivation in Juvenile Coho Salmon Exposed to Dissolved Copper under Varying Water Chemistry Conditions, including Additions and Corrections as prepared by McIntyre et al. *Late filing; accepted at Public Hearing 10.02.16
- 5.4.11 EARP Monitoring Overview Chart. Project: Carmacks Copper Pilot Heap Leach Plant, Carmacks. *Late filing; accepted at Public Hearing 10.02.17
- 5.5 J. Kruse, Selkirk Renewable Resources Council, 10.01.25
- 5.6 J. Miller, Environment Canada, 10.01.25
- 5.7 R. Lamb, YG - Yukon Environment, 10.01.25
- 5.7.1 Attachment 1 - Curriculum Vitae - David Flather, Lorax Environmental, 10.01.25
- 5.7.2 Attachment 2 - Review of Proposed Effluent Discharge Standards, 10.01.25
- 5.7.3 Attachment 3 - Site Specific Water Objectives - Copper, 10.01.25
- 5.8 R. Lamb, YG - Yukon Environment, Replacing Exhibit 5.7, 10.02.01 *Late filing; accepted at Public Hearing 10.02.15
- 5.9 R. Moar, Little Salmon Carmacks First Nation, 10.02.09 *Late filing; accepted at Public Hearing 10.02.15
- 5.9.1 Mining Claims Map 115/07
- 5.9.2 Mining Claims Map 115/10
- 5.9.3 N. de Graff, Can-nic-a-nick Environmental Sciences, Identification of chinook and fall chum salmon spawning habitat in the Yukon River mainstem between Tatchun Creek and Minto, Yukon Territory
- 5.10 R. Lamb, YG - Yukon Environment, Retracting Exhibit 5.7.3, 10.02.15 *Late filing; accepted at Public Hearing 10.02.15
- 5.11 Little Salmon/Carmacks First Nation provided a document titled, “Letter of Understanding Between Little Salmon Carmacks First Nation and Government of Yukon Department of Energy, Mines and Resources, signed January 2010 *Late filing; accepted at Public Hearing 10.02.19
- 5.12 Little Salmon/Carmacks First Nation provided a document titled, “The progression of metallurgical testwork during heap leach design, written by S.W. Robertson and P.J. Van Staden *Late filing; accepted at Public Hearing 10.02.19
- 5.13 Little Salmon/Carmacks First Nation letter presenting additional documents pertaining to 1993/94 Field Scale Trial by Western Copper Holdings Ltd., 10.02.25 *Late filing; accepted at Public Hearing 10.03.01
- 5.13.1 Williams Creek Project, A Proposal for Funding to Operate a Solvent Extraction Pilot Plant for Williams Creek Copper Ore, prepared by Western Copper Holdings Ltd. August 1993
- 5.13.2 Letter from Western Copper Holdings Ltd. to Northern Affairs Program regarding the Completion of the Pilot Leach Test, dated 94.02.23
- 5.13.3 Letter from Western Copper Holdings Ltd. to Northern Affairs Program regarding Pilot Plant Neutralization, dated 94.05.02
- 5.13.4 Letter from Northern Affairs Program to Western Copper Holdings Ltd. regarding the EARP Overview Monitoring Chart to monitor progress of the Solvent Extraction/Electrowinning Pilot Project at Carmacks, dated 94.04.25
top
VOLUME XI
6. RESPONSES TO INTERVENTIONS
- 6.1 Carmacks Copper Ltd. Responses to Interventions, Type A Water Licence Application QZ08-084, Carmacks Copper Project, dated March 2, 2010 *Late filing; accepted at Public Hearing 10.03.02
- 6.2 Carmacks Copper Ltd. Slide Presentation for Responses to Interventions *Late filing; accepted at Public Hearing 10.03.02
7. CURRENT/PREVIOUS WATER USE LICENSE(S)
9. YESAA
- 9.1 Project Confirmation Form, 09.10.29
- 9.2 Decision Document, 09.10.29
10. DECISION
11. TRANSCRIPT OF PUBLIC HEARING
12. OTHER
- 12.1 Presentation by Carmacks Copper Ltd., 10.02.15 *Presented & accepted at Public Hearing 10.02.15
- 12.1.a Proposed Mine Assessment and Permitting
- 12.1.b Location, Geology and Mineralization
- 12.1.c Environmental Setting Management Plan
- 12.1.d Water Licence Overall Objective
- 12.1.e Site Specific Water Quality Objectives
- 12.1.f Closure and Reclamation